Milestones
- April 2026 - Schematic Design Complete. Project estimating in process
- March 2026 - Stakeholder Meetings in Process
- March 2026 - CM/GC Contractor RFP in Process
Project Timeline

Now - Design/Permits/Bidding
June 2027 - Break Ground
August 2027 - End of summer work - Transition to occupied construction
September 2027 - June 2028 Limited work - Occupied construction
June 2028 - August 2028 - Summer work
August 2028 - Tentative Project Complete