Fowler Middle School

A modern, rectangular building with a metal roof and blue-framed windows, surrounded by trees and a paved parking area in the foreground.

Milestones


  • June 2026 - Design Development Complete
  • May 28, 2026 - Fowler Design Advisory Committee Meeting #08.  Fowler Middle School Library 4:15-5:45 pm
  • May 15, 2026 - Land Use Submission to City of Tigard. 
  • April 28, 2026 - Neighborhood Meeting. Fowler Middle School Commons 6-8 pm
  • April 28, 2026 - Fowler Design Advisory Committee Meeting #07. Fowler Middle School Library 4-5:30 pm
  • April 13, 2026 - Fowler Design Advisory Committee Meeting #06.  Fowler Middle School Library 4-5:30 pm
  • April, 2026 - Design Development Begins
  • March 2026 - Schematic Design Complete. Project estimating in process
  • March 05, 2026 - Fowler Design Advisory Committee Meeting #05. Fowler Middle School Library 4-5:30 pm
Fowler middle school campus conceptual graphic top view.
Fowler Conceptual Image: Lush green trees frame a modern school building with a glass entrance, while a paved walkway leads towards it in the foreground.
An aerial view shows Fowler Middle School with a portion of the structure marked to remain, surrounded by trees, a baseball field, and a track, with SW Walnut Street and SW Tiedeman Avenue visible in the foreground and background respectively.
A schematic design for Fowler Middle School's outdoor spaces shows a football field and track in the foreground, with the school building and surrounding grounds in the background, featuring designated drop-off areas and service zones.
A schematic floor plan of a school building, with colored sections representing different areas, is presented against a white background with text overlays.
A conceptual rendering of a renovated gymnasium shows people on the polished wooden floor in the foreground, with bleachers and architectural details visible in the background.

Project Timeline

The image shows a timeline for the construction and completion of Fowler Middle School, including key milestones such as the groundbreaking, building occupancy, and the estimated completion date.

Now  - Design/Permits/Bidding

June 2027 - Break Ground on Phase I (Build new building)

July 2029 - Phase II - (Demo old building and site work)

September 2029 - Occupy New Building

August 2030 - Campus Construction Complete