Durham Elementary School

A commercial building with a red roof and a parking lot in the foreground, surrounded by pine trees in the background.

Milestones

Project Timeline

The image presents a timeline for the Durham Elementary school, outlining various construction and renovation activities scheduled to take place from 2026 to 2029.

Now - Design/Permits/Bidding

June 2028 - Break Ground

August 2028 - End of summer work - Transition to occupied construction

September 2028 - June 2029 Limited work - Occupied construction

June 2029 - August 2029 - Summer work

August 2029 - Tentative Project Complete

June 2029 - Break Ground