Milestones

Project Timeline

The image is a timeline depicting the construction schedule for Byrom Elementary, including the estimated completion dates for various phases of the project.

Now - Design/Permits/Bidding

June 2027 - Break Ground

August 2027 - End of summer work - Transition to occupied construction

September 2027 - June 2028 Limited work - Occupied construction

June 2028 - August 2028 - Summer work

August 2028 - Tentative Project Complete