Woodward ES - Completed
Ribbon Cutting Ceremony
There are no resources or collections to display
Bond Construction Update - August 2019
Secure vestibule and other building renovations
Bond construction projects will begin this summer in June 2019
The school will be closed with very limited to no access during construction
Bond Construction Update - May 2019
2019 Construction Plans
Project Details
Architect | BORA Architects
General Contractor | Inline
Groundbreaking | June 2019
Anticip. Completion | Oct 2019
Budget | $1.3 Million
Status | Completed
Timeline
Nov 2016 - Bond Passed
Dec 2016 - Programming Kick-off
Jan 2017 - Schematic Design
Feb 2017 - Design Dev.
Mar - Oct 2018 - Project Hiatus
Nov 2018 - Construction Docs
June 2019 - Groundbreaking
June - Sep 2019 - Construction
Sep 2019 - Construction Complete