Twality MS - Completed

News 

Triplett Wellman

Important Memorandum

Regarding Governor Brown's Executive Order 20-12

Twality new commons

Construction Update April 2020

Framing second story classroom wing and pouring gym foundation

alt-text

Construction Update - June 2019

Campus closed for the summer and offices located at C.F. Tigard Elementary

No post to display.

Project Details

Architect | IBI Group
CMGC | Triplett Wellman

Groundbreaking | June 2019
Anticip. Completion | Fall 2021
Construction Budget | $46 M

Status | Construction

* Dates are subject to change

Timeline

Nov 2016 - Bond Passed
Jan 2017 - Programming Kick-off
May 2017 - Schematic Design
Jul '17 - May '18 - Sched. Hiatus
May 2018 - Design Dev.
Sep 2018 - Construction Docs
June 2019 - Groundbreaking
June '19 - Jan '21 - Construction
January 2021 - Completed