Skip To Main Content

Metzger ES - Completed

There are no resources or collections to display

Construction is Completed

New vestibule provides a more secure main entrance to the building

Metzger Elementary Secure Vestibule is now complete and provides a more secure main entrance to the building. When school resumes, our school will have a new protocol for entering the building:

  • All school visitors will proceed to the main entrance of the school and enter the secure vestibule through the main doors at the front of the building.
  • Once inside the vestibule, visitors will find that the door to the main office is locked. If the visitor is immediately recognized as a known parent, guardian or volunteer, they will be “buzzed in” to the main office by office staff. 
  • Visitors inside the vestibule that are not immediately recognized will press the two-way video intercom button located inside the vestibule which will ring the phones in the main office so that office staff can greet the visitor and establish their purpose for visiting.  Once the visitors' purpose is verified, they will be buzzed into the main office.

The vestibule is one more way that we can keep our school safe for students, families, and staff.

summer construction

Metzger Construction Update

When this project is completed at the conclusion of this summer, we will have a secure front entrance

Architect | Oh planning + design, architecture
General Contractor | Inline

Groundbreaking | May 2020
Anticip. Completion | August 2020
Budget | $361k

Status | Construction

Nov 2016 - Bond Passed
Jan 2017 - Programming Kick-off
May 2017 - Schematic Design
Jul '17 - May '18 - Sched. Hiatus
May 2018 - Design Dev.
Sep 2018 - Construction Docs

May 2020 - Groundbreaking
May - Aug 2020 - Construction
Aug 2020 - Construction Complete