Durham ES - completed

Durham Entrance

Ground Breaking and Grand Opening Celebrations

There are no resources or collections to display
Construction Update

Bond Construction Update - August 2019

New secure vestibule entry and other construction updates

alt-text

Bond construction projects will begin this summer in June 2019

Image of Durham Elementary building

Bond Construction Update - May 2019

2019 Bond construction plans

Project Details

Architect | BORA Architects
General Contractor | Inline

Groundbreaking | June 2019
Anticip. Completion | Oct 2019
Budget | $1.3 Million

Status | Completed

Timeline

Nov 2016 - Bond Passed
Dec 2016 - Programming Kick-off
Jan 2017 - Schematic Design
Feb 2017 - Design Dev.
Mar - Oct 2018 - Project Hiatus
Nov 2018 - Construction Docs
June 2019 - Groundbreaking
June - Sep 2019 - Construction
Sep 2019 - Construction Complete