Byrom ES - completed

Byrom Elementary

Byrom Entrance

Construction and Completion Gallery

There are no resources or collections to display

Bond Construction Completed

Byrom ES celebrated the Grand Opening of the new Main Office and Secure Vestibule on September 3, the first day of school. This investment in Byrom Elementary School was made possible by the generous support of Tigard-Tualatin School District Voters.

The new main office was brought to the front of the school and renovation work included the addition of exterior windows to provide better visibility from the office to the parking lot.  

Renovations also include the following improvements: 

  • New Counseling Office and renovated Classroom in location of former Main Office
  • Restroom Improvements
  • New Cafeteria Flooring
  • Secure vestibule requireing visitors to be “buzzed” into the main office prior to gaining access to the main body of the school.

Ribbon Cutting Ceremony

Secure vestibule and other renovations to the building

Bond Construction Update - August 2019

Secure vestibule and other building renovations

alt-text

Bond Construction Update - May 2019

We are getting closer to the big remodel here at Byrom!

Project Details

Architect | BORA Architects
General Contractor | Inline

Groundbreaking | June 2019
Anticip. Completion | Oct 2019
Budget | $1.3 Million

Status | Completed

* Dates are subject to change

Timeline

Nov 2016 - Bond Passed
Dec 2016 - Programming Kick-off
Jan 2017 - Schematic Design
Feb 2017 - Design Dev.
Mar - Oct 2018 - Project Hiatus
Nov 2018 - Construction Docs
June 2019 - Groundbreaking
June - Sep 2019 - Construction
Sep 2019 - Construction Complete