Bridgeport ES - completed
Bridgeport Elementary
Grand Opening Ceremony Held for Bridgeport ES Main Office & Secure Vestibule
Bridgeport ES celebrated the Grand Opening of the new Main Office and Secure Vestibule on September 13 at Back to School Night. One of the first major project completed under the TTSD School Bond Program, construction at Bridgeport kicked off in May 2018.
The new main office was brought to the front of the school, relocated in the former location of a classroom. Renovation work included the addition of exterior windows to provide better visibility from the office to the parking lot. Ther former main office was converted into a classroom and counseling office.
Project Details
Architect | BORA Architects
General Contractor | TS Gray
Groundbreaking | June 2018
Anticip. Completion | Oct 2018
Budget | $1.3 Million
Status | Complete
* Dates are subject to change
Timeline
Nov 2016 - Bond Passed
Dec 2016 - Programming Kick-off
Jan 2017 - Schematic Design
Feb 2017 - Design Dev.
Mar - Oct 2017 - Project Hiatus
Nov 2017 - Construction Docs
June 2018 - Groundbreaking
June - Sep 2018 - Construction
Sep 2018 - Construction Complete