Twality Middle School Construction



News
-
Construction Update - June 2019
Campus closed for the summer and offices located at C.F. Tigard Elementary
-
Bond construction projects will begin this summer in June 2019
The school will be closed with very limited to no access during construction
Project Details
-
Architect | IBI Group
CMGC | Triplett Wellman
Groundbreaking | June 2019
Anticip. Completion | Fall 2021
Construction Budget | $46 MStatus | Construction
* Dates are subject to change
Timeline
-
Nov 2016 - Bond Passed
Jan 2017 - Programming Kick-off
May 2017 - Schematic Design
Jul '17 - May '18 - Sched. Hiatus
May 2018 - Design Dev.
Sep 2018 - Construction Docs
June 2019 - Groundbreaking
June '19 - Jan '21 - Construction
Fall 2021 - Anticipated Opening