Fowler Middle School

Fowler front entrance

Project Details

  • Architect | BORA Architects
    General Contractor | Fortis Construction

    Groundbreaking | May 2017
    Anticip. Completion | Nov 2017
    Budget | $6.8 Million 

    Status | Complete

    * Dates are subject to change

Timeline

  • Nov 2016 - Bond Passed
    Dec 2017 - Programming Kick-off
    Jan 2017 - Schematic Design
    Feb 2017 - Design Dev.
    June 2017 - Groundbreaking
    June - Nov 2017 - Construction
    Sep 2017 - Phase I: Office Opens
    Nov 2017 - Phase II: Science Labs Open
    Project Complete