Project Details

  • Architect | BORA Architects
    General Contractor | TS Gray

    Groundbreaking | Feb 2018
    Anticip. Completion | Spring 2018
    Budget | $6 Million

    Status | Construction

    * Dates are subject to change

Timeline

  • Nov 2016 - Bond Passed
    Mar 2017 - Programming Kick-off
    May 2017 - Schematic Design
    June 2017 - Design Dev.
    July 2017 - Construction Docs
    Feb 2018 - Groundbreaking
    Feb '17 - Nov '18 - Construction
    Jan 2019: Addition Opens